You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?
Correct Answer: B
Explanation/Reference: Explanation: Parametric estimates are created for repetitive tasks, such as four hours per unit installed; 1,000 units to install would equate to 4,000 hours. A template does not address this type of time estimating directly. A template for time estimating is an analogous estimate type. A template for any project is an activity list or a part of the activity list from a previous project. The template contains the activity attributes information and other vivid information that are helpful to define activities. It is also used to classify schedule milestones. Incorrect Answers: A: Templates do indicate milestones. C: Templates can save time for the project manager and the project team. D: Templates can include activity attribute information.