Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project's ability to finish by a given deadline?
Correct Answer: C
Explanation/Reference: Explanation: Of all the constraints listed only this is an external dependency, which can directly affect the project manager's control over the project work. If the BGH company is late delivering the software portion of the project, it will likely have an effect on the project's ability to complete the project on time. Incorrect Answers: A: This is only constraint if the project team members are not available, or do not have the required skills to complete the project work. B: While regulations may affect the project timing, this is not the best choice. D: The $1,250,000 is an example of cost constraint.