You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?
Correct Answer: B
Explanation/Reference: Explanation: Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to Activity F, the project will now take 35 days to complete. Incorrect Answers: A, C, D: These are not the valid answers.