You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project. What approach would you recommend to condense the project duration?
Correct Answer: A
Explanation/Reference: Explanation: Of all the choices, only fast tracking is an option that would not increase project costs. Fast tracking allows phases of the project to overlap, but it does increase project risks. Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. Incorrect Answers: B: Crashing adds labor to the project and increases project costs. C: Effort-driven activity analysis examines activities whose duration may be reduced by adding labor. This approach, however, increases project costs, as it is a form of project crashing. D: Rewards and recognitions are good incentives for the project team, but simply offering the reward does not decrease the duration of the project.