Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?
Correct Answer: C
Explanation/Reference: Explanation: The performance measurement baseline, which can be comprised of cost, scope, and schedule, is the foundation for creating a performance report. Incorrect Answers: A: Cost variances and the cost performance index are cost values that must be considered along with the scope performance and schedule performance. B: The scope baseline will only reflect the performance of the scope, whereas performance reports typically need scope, time, and cost as its foundation. D: Only reporting performance on the schedule is not enough for a performance report. Laura should also report on scope and cost at a minimum.