Valid PMI-SP Dumps shared by ExamDiscuss.com for Helping Passing PMI-SP Exam! ExamDiscuss.com now offer the newest PMI-SP exam dumps, the ExamDiscuss.com PMI-SP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-SP dumps with Test Engine here:
You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?
Correct Answer: C
Explanation/Reference: Explanation: The precedence diagramming method is not a tool and technique that will be used during the activity definition process. Precedence diagramming method (PDM) is used in critical path methodology for building a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities, and join each other with arrows that show the logical relationship that exists between them. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining activities.