Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?
Correct Answer: C
Explanation/Reference:
Explanation:
Risk events are not associated with the activity attributes, but are recorded in the project risk register. Risk events are the distinct and particular occurrence that negatively affects a decision or a plan. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports.