Della works as a Project Manager for BlueWell Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?
Correct Answer: A
Explanation/Reference: Explanation: According to the question, the schedule variance (SV) of the project is zero. A value of 0 indicates that the project is right on target. Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. Incorrect Answers: B: The positive SV depicts that the project is ahead of the planned schedule. C: The negative SV means that project is behind the schedule. D: This result can be drawn by looking at the cost variance (CV) of the project.