You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?
Correct Answer: D
Explanation/Reference: Explanation: Change requests are an output of performance report, and allow the project manager to address corrective actions and preventive actions to help the project get back in alignment with performance baselines. Incorrect Answers: A: Updating the organizational process assets is an important activity, but it does not address the poor performance directly. B: While performance reports are an output of the performance reporting, these reports do not specifically address the problems in the project. C: Performance re-baselining is not an output of performance reporting so this choice is not valid.