Your team has identified the risks on the project and determined their risk score. The team is in the midst of determining what strategies to put in place should the risks occur. After some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. Although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. Which of the following is true regarding this question?
Correct Answer: D
This is a response strategy known as passive acceptance because the team has decided to take no action and make no plans for the risk. This is a strategy that can be used for either positive or negative risks.