There is a project with CPI = 0.81 and TCPI = 1.00001; this project is:
Correct Answer: C
CPI less than 1.0 tells us that we are Over-budget.The To-Complete-Performance-Index (TCPI) calculates an efficiency factor, which must be attained, if the remaining works to be completed within the forecasted EAC. So, TCPI of 1.00001 means it looks achievable. That means, this project is Over-Budgeted but can be recovered Answer C is closest of all.