Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
Each Organization measures project team performance in its own way. However on which combination of the following objectives do most managers seem to agree?
Correct Answer: C
"Project Team Performance" surely will not be right if project result does not maintain `technical specification' (it's a Scope) hence choice D is out. Other two important components of Triple Constraints are Time and Cost. Choice A has only Scope and Cost. All three (Scope, Time and Cost) are covered in choice C and B. But many organization may not give much importance to the fourth factor ` Team members' professional growth' of choice B, as the project may be done under contract and buyer company may not be interested on this aspect, at all. Hence, the right choice is C.