You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Its products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. You have documented the characteristics of the product and its functionality using which of the following tools and techniques?
Correct Answer: B
The key to this question was that the characteristics of the product were documented with this tool. Configuration management documents the physical characteristics and the functionality of the product of the project.