You have been recently assigned to provide an accurate project schedule for a large construction company. You are evaluating the network diagram for the construction project. Your lead engineer has given you the following estimates for several critical path activity: 30 days (optimistic), 80 days (pessimistic), and 40 days (most likely). Which of the following statements are true, assuming the beta distribution?