You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs. You've attempted to gain the cooperation of the business analyst working on this project, and you need some answers. She is elusive and tells you that this project is not her top priority. What should you do to avoid situations like this in the future?
Correct Answer: B
The best answer to this question according to the PMBOK Guide standard is to negotiate with the functional manager to participate in the business analyst's annual performance review. D is an appropriate response but doesn't include the PMBOK Guide's direction that the project manager should participate in the performance review.