Which of the following is NOT an output of the Close Project process?
Correct Answer: C
The project management methodology describes the process that you use to manage your project. It really doesn't have anything to do with closing the project. The other three answers, however, do! You need project closure documents to show that the project really was closed out. You gather all of the project les together so that they can be archived. And formal acceptance documentation is what you get from your customer that tells you they've approved the final product.