You have been recently been assigned to provide an accurate project schedule for a large construction project. You are evaluating the network diagram for the construction project. Your lead engineer has given you following estimates for critical path activity: 30 days (optimistic), 100 days (pessimistic), and 50 days (most likely). What is the standard deviation for this activity, assuming a beta distribution?