Project coordination is enhanced through progress reporting, variance reporting, and cross- team meetings. These are all forms of:
Correct Answer: D
When reporting performance and variance, we do it within the project team as well with stakeholders. I would like to consider stakeholder meetings as cross-team meetings to support my answer of "D". However, if the cross-team meetings are for non-project related teams for lessons' learned, then the activities in the question seem serves quality management.