You are performing actions such as reporting and comparing actual project results against the project management plan, analyzing performance data and determining whether corrective or preventive action should be recommended, documenting all appropriate product information throughout the life of the project, gathering and recording project information, and monitoring approved change requests. Which process are you performing?
Correct Answer: B
The Monitor and Control Project Work process involves reporting and comparing project results, gathering and recording data, recommending actions, and monitoring approved change requests.