This process uses tools like decomposition and rolling-wave planning to produce the activity list and other outputs. Because of the purpose of this process, which of the following is considered its primary input?
Correct Answer: A
This question is describing the Activity Definition process. The purpose of this project is to decompose the work package elements of the WBS into activities. The WBS is the primary input of this process.