You've constructed the WBS for your recent project. You've requested that the subproject managers report to you in three weeks with each of their individual WBSs constructed. Which statement is not true regarding the subproject managers' WBS?
Correct Answer: B
The work package level is the lowest level in the WBS and facilitates resource assignment and cost and time estimates. The agreed-upon deliverables in C would appear in the higher levels in the WBS.