You are the project manger for Xylophone Phonics. It produces children's software programs that teach basic reading and math skills. You are performing the Quality Planning process and are identifying nonproductive activities. Part of this involves capturing information such as process boundaries, process configurations, and process metrics. Which of the following does this describe?
Correct Answer: A
This describes the process improvement plan, which is a subsidiary of the project management plan and an output of the Quality Planning process.