You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Its products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB?
Correct Answer: B
Configuration control boards (CCBs) review change requests and have the authority to approve or deny them. Their authority is defined by the organization.