Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders to define the scope. The sponsors mentioned that the gazebo is a really important part of their daughter's wedding ceremony that was planned for 7 months from then. In fact, they said that if the gazebo couldn't be completed in 7 months, it wouldn't be worth it for them to even start the project. Dave wrote down the 7-month deadline to put in his Project Scope Statement. In which section of the document did the deadline appear?
Correct Answer: C
Since the project absolutely must be completed in 7 months for it to be worth doing, the deadline is a constraint. It must be met for the project to be considered successful.