Mike is a project manager for an IT technology implementation project. He is using an ishikawa diagram to figure out what could cause potential risks on his project. Which process is he doing?
Correct Answer: D
Diagramming Techniques (including Ishikawa diagrams and Flowcharts) are a tool of the Risk Identification process. You use them to find the root cause of defects in Quality Management processes but they can also be useful in finding the risks that can lead to trouble in Risk Management.