You have been assigned to a project to construct a 18-hole golf course, featuring 7,500 yard, par-72 course that has a magnificent tropical setting. You've calculated the estimated project completion date. However the estimated completion date is 5 months after the desired completion date. After analyzing the project network diagram, you've determined that many of the activities have discretionary dependencies. To decrease the project duration you've requested additional resources, but were told that NO additional resources are available for your project. Assuming that the project has low risks, which of the following is the BEST plan of action?