You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300, AC = 200, and EV = 250. What do you know about this project?
Correct Answer: B
The CV is a positive number and is calculated by subtracting AC from EV as follows: 250 - 200 = 50. A positive CV means the project is coming in under budget, meaning you've spent less than you planned as of the measurement date.