Measuring the probability and consequences of risks is part of
Correct Answer: C
My opinion, the key word in this question is "Measuring". This would imply D - quantitative risk analysis. It would not be A, because Risk Management Planning deals with your general approach to managing risk, not with specific risks. Risk Identification doesn't involve any estimation of the probability of a risk or the impact. Qualitative Analysis involves a broad determination of the probability and impact of risks, but I would argue that there is no "measurement" done in qualitative analysis.