Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
Together with your team, you applied three-point estimation on a Critical path which consists of two activities. The following duration uncertainties are all calculated assuming a +-3sigma Confidence interval. The duration uncertainty-defined as pessimistic minus optimistic estimate-of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula, what is the duration uncertainty of the entire path?