Your project is using complex, unproven technology. Your team conducted a brainstorming session to identify risks. Poor allocation of project resources was the number one risk. This risk was placed on the risk register, which included at this point a______________
Correct Answer: B
Explanation/Reference: Explanation: The risk register is prepared first in the identify risks process. It contains a list of identified risks in as much detail as possible and a list of potential responses when they are identifiable at this time.