Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
You work for a telecommunications company, and when developing a project management plan for a new project, you found that you must tailor some company processes because the product is so different than those products typically produced by your company. To tailor these processes, you will follow______________.
Correct Answer: A
Explanation/Reference: Explanation: Standardized guidelines and work instructions are an organizational process asset to consider as the project management plan is developed. They include guidelines and criteria to tailor the organization's set of standard processes to satisfy the specific needs of the project.