Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing. PV = $2,200 EV = $2,000 AC = $2,500 BAC = $10,000 What is the CPI for this project, and what does it tell us about cost performance thus far?
Correct Answer: B
Explanation/Reference: Explanation: CPI is calculated as EV/AC (in this case, $2,000/$2,500). EV measures the budgeted dollar value of the work that has actually been accomplished, whereas AC measures the actual cost of getting that work done. If the two numbers are the same, work on the project is being accomplished for exactly the budgeted amount of money (and the ratio will be equal to 1.0). If actual costs exceed budgeted costs (as in this example), AC will be larger than EV, and the ratio will be less than 1.0. CPI is also an index of efficiency. In this example, an index of 0.80 (or 80 percent) means that for every dollar spent on the project only 80 cents worth of work is actually accomplished.