Having prepared stakeholder management plans on previous projects, you know it is positive to review the project management plan because it______________
Correct Answer: D
Explanation/Reference: Explanation: Among other key items useful in the project management plan to review while preparing the stakeholder management plan is the change management plan. All projects involve some type of change. Reviewing this plan can help the project manager work with stakeholders who may be resistant to the project to help turn them into ones who are supportive or at least neutral to the resulting changes.