A number of organizational process assets are useful as inputs to the manage stakeholder engagement process. Similarly a number of organizational process assets require updates because of this process. An example of one that is an input is______________
Correct Answer: B
Explanation/Reference: Explanation: Historical information about previous projects, organizational communications requirements, issue management procedures, and change control procedures are examples of organizational process assets that can influence the manage stakeholder engagement process.