You are the project manager for a two-year project that is now beginning its second year. The mix of team members has changed, and there is confusion as to roles and responsibilities. In addition, several of the completed work packages have not received the required sign-offs, and three work packages are five weeks behind schedule. To gain control of this project, you need to______________
Correct Answer: C
Explanation/Reference: Explanation: The responsibility assignment matrix defines project roles and responsibilities in terms of work packages and activities. It can be used to show who is a participant, who is accountable, who handles review, who provides input, and who must sign off on specific work packages or project phases.