Any step recommended to bring expected future performance in line with the project management plan is called______________
Correct Answer: B
Explanation/Reference: Explanation: Recommended corrective action is an output from control scope. In addition to bringing expected future performance in line with the project management plan, it also serves to bring expected future performance in line with the project scope statement.