You are leading a team to recommend an equitable reward and recognition system for project managers. Before finalizing the plan, you want to ensure that executives understand the basic objective of reward systems. This objective is to______________
Correct Answer: B
Explanation/Reference: Explanation: Reward and recognition systems are formal management actions that provide an incentive to behave in a particular way, usually with respect to achieving certain goals. Such systems are described in the staffing management plan. A best practice is to give the team recognition throughout the life cycle.