Ideally, a project manager should be selected and assigned at which point in the project life cycle?
Correct Answer: A
Explanation/Reference: Explanation: When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization.