Two key inputs to the perform quantitative risk analysis process are the______________
Correct Answer: C
Explanation/Reference: Explanation: The cost and schedule of a project are two areas significantly affected by risk occurrences. Information on these two areas, because of their quantitative nature, provides excellent input to the perform quantification risk process to help determine overall impact and to provide guidelines as managing risk reserves.