Constant bickering, absenteeism, and substandard performance have characterized the behavior of certain members of your team. You have planned an off-site retreat for the team to engage in a variety of activities. Your primary objective for investing time and money in this event is to improve______________
Correct Answer: A
Explanation/Reference: Explanation: Team development leads to improved team performance, which ultimately results in improved project performance. Improvements in team performance can come from many sources and can affect many areas of project performance. For example, improved individual skill levels such as enhanced technical competence may enable team members to perform their assigned activities more effectively. Team development efforts have greater benefit when conducted early but should take place throughout the project life cycle.