The project scope statement should be used in the identify risk process because it______________
Correct Answer: A
Explanation/Reference: Explanation: Project assumptions, which should be enumerated in the project scope statement, are areas of uncertainty, and as such are potential causes of project risk. The scope statement and the WBS are part of the scope baseline, an input to identify risks.