The software development company has recently been awarded a large contract to create a new animation software program. This will require the company to move into a new office complete with production facilities twice their current size. The schedule is tight for this new project. The new facility is behind schedule with the cubicles and network wiring on pace to finish three weeks late. If this can't be done on time and will slip three weeks, the company has decided there is nothing it can do, and it will simply deal with the consequences. This is an example of what type of risk response?