Decomposition is a technique used for both WBS development and activity definition. Which following statement best describes the role decomposition plays in activity definition as compared to creating the WBS?
Correct Answer: C
Explanation/Reference: Explanation: Final output is described as schedule activities. In the create WBS process, final output is described as deliverables or tangible items. In the define activities process, final output is described as activities.