Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
You must consider direct costs, indirect costs, overhead costs, and general and administrative costs during cost estimating. Which of the following is NOT an example of a direct cost?
Correct Answer: D
Explanation/Reference: Explanation: Direct costs are incurred for the exclusive benefit of a project (for example, salary of the project manager, materials used by the project, and subcontractor expenses). Indirect costs, also called overhead costs, are allocated to a project by its performing organization as a cost of doing business. These costs cannot be traced to a specific project and are accumulated and allocated equitably over multiple projects (for example, security guards, fringe benefits, and electricity).