Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
Correct Answer: D
Explanation/Reference: Explanation: The project manager's ability to influence project decisions increases the higher up he or she______________and the person to whom he or she reports______________is placed in the organization. In the strong matrix, the project manager's authority ranges from moderate to high.