You are the project manager for the construction of an incinerator to burn refuse. Local residents and environmental groups are opposed to this project. Management agrees to move this project to a different location. This is an example of which one of the following risk responses?
Correct Answer: D
Explanation/Reference: Explanation: Risk avoidance involves changing the project management plan to eliminate the threat entirely.