The risk urgency assessment is a tool and technique used for______________
Correct Answer: C
Explanation/Reference: Explanation: Risks that may happen in the near-term need urgent attention. The purpose of the risk urgency assessment is to identify those risks that have a high likelihood of happening sooner rather than later. It is combined with the risk ranking to give a final risk severity ranking.