Which one of the following represents a constraint on the acquire project team process?
Correct Answer: B
Explanation/Reference: Explanation: Staff assignments in organizations are governed by the policies, procedures, or guidelines of individual components. These policies will constrain the project manager's actions in acquiring a project team. The more familiar the project manager is with such policies, the easier it will be for him/her to assemble a team. Such recruitment practices are examples of personnel administration policies; an enterprise environmental factor, which is an input to acquire project team.