As you use the critical chain method in lieu of the critical path method in developing your schedule, assume you have determined the buffer schedule activities. Your planned activities are scheduled to their latest possible planed start and end dates. Therefore, you are focusing on______________
Correct Answer: C
Explanation/Reference: Explanation: The purpose of the critical chain method is to modify the project schedule to account for limited resources. The schedule is built using duration estimates with required dependencies and defined constraints as inputs. Then, the critical path is calculated and resource availability is entered, which means there is a resource-limited schedule with an altered critical path. Buffers protect the critical chain from slippage, and the size of each buffer accounts for the uncertainty in the duration of the chain of dependent tasks that lead up to the buffer. This method then focuses on managing the remaining buffer durations against the remaining duration of task chains.