You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing. PV = $2,200 EV = $2,000 AC = $2,500 BAC = $10,000 The CV for this project is______________
Correct Answer: D
Explanation/Reference: Explanation: CV is calculated as EV - AC (in this case, $2,000 - $2,500). A negative CV means that accomplishing work on the project is costing more than was budgeted.